Key West-to-East Power Transmission UHV hub completes 10th annual overhaul in Shaoxing
As a critical artery of China's West-to-East Power Transmission project, the ±800 kV UHV Shaoxing Converter Station has launched its 10th annual maintenance campaign. On November 8, maintenance staff worked meticulously inside the station's valve hall to inspect and replace sealing rings at water pipe joints of valve towers, eliminating potential leakage risks stemming from rubber component aging. This overhaul marks the tenth annual systematic upgrade since the commissioning of the Lingshao UHV DC transmission project.
The comprehensive maintenance officially commenced on November 3 and will last 16 days with both bipolar DC systems fully shut down. The maintenance schedule covers 7 days of DC system overhaul, 8 days of AC filter inspection, and 15 days of calibration work for tuning and camera equipment. A total of 104 maintenance tasks are underway simultaneously, including overhauling four sets of AC filters as well as No.1 and No.2 modulation camera units.
After a decade of continuous operation, equipment at the Shaoxing Converter Station has entered its mid-service cycle, bringing prominent challenges of aging facilities and compact operational layout. Over the past ten years, the station has recorded 7,392 equipment defects, with 53 percent emerging in the latest three years alone. To eliminate hidden hazards, this year's overhaul includes nine major renovation categories: reinforcement of 15 current-transformer switch head covers, replacement of 16 V-string suspension insulator sets, renewal of 54 valve-controlled optical receiver boards, retrofitting of 977 residual current sensors, and sampling inspection of 224 valve tower water pipe seals.
Alongside facility upgrades, the independent maintenance team of State Grid Zhejiang Ultra-High Voltage Company has achieved remarkable growth. Back in 2015, during the first independent overhaul of the Jinhua station, the team only had 15 professional technicians. The team has now expanded to 106 members with full Class-C independent maintenance capabilities for UHV facilities.
This year's annual inspection features fully digital and intelligent management throughout the whole process. One week ahead of construction, technicians completed simulated rehearsals for 207 power outage procedures covering 3,185 operational steps on a digital simulation platform. On-site staff verified 84 pre-operation checklists and more than 5,000 inspection items one by one, ensuring full-process traceability and standardized construction.
According to the official schedule, the station's bipolar DC systems will be re-energized on November 18. Upon completion of the overhaul, the Shaoxing Converter Station will operate with enhanced stability to pursue zero unplanned outages and zero locking incidents throughout the year, solidifying reliable power supply for peak winter electricity demand and supporting the stable operation of China's cross-regional power transmission network.